Work · Former Colegios Provinciales
Repairing exposed concrete with corroded reinforcement, and the roofs, of two office buildings in use
Two 1970s buildings whose exposed concrete was damaged by corrosion of the reinforcement. We are breaking out and repairing more than 1,000 m² with structural mortar and rebuilding the roofs with the buildings in use. Works in progress.

Objective
The El Carmen and Fernando III buildings are two of the three former Colegios Provinciales in Córdoba, designed in 1971 by Rafael de La-Hoz Arderius as a school residence. The Diputación is remodelling them to bring its services together there. The first phase was let in three lots, and the first is ours: the structural repair and the roofs, and the works for accessibility and fire escape.
The starting problem is the exposed concrete. The façades are formed by deep beams and reinforced-concrete columns open to the weather, and the reinforcement has corroded through damp and carbonation. The project’s study of defects, by CEMOSA, records damp stains, cracks, spalling and rust stains. The waterproofing of the roofs, moreover, is at the end of its service life.
Difficulties
- An earlier repair that did not last. In 1995 the reinforcement was already cleaned and the concrete made good with mortar. That mortar has cracked and come away, and the damage has reappeared.
- The real extent is only known on breaking out. The project marks the damaged areas on the elevations, but the extent of each is checked when the loose concrete is removed.
- Buildings in use. Fernando III is fully occupied by offices of the Diputación and of its companies and agencies. In El Carmen the ground floor houses offices of the regional and national employment services.
- Protected architecture. The buildings are listed in the Iberian DOCOMOMO register and in Córdoba’s Catalogue of Protected Assets. The repair cannot alter their appearance.
- Demolishing reinforced concrete inside the building. The new escape routes mean cutting deep façade beams and walls of the central stair core.
- Three lots in sequence. The ventilated façade of lot 2, by another contractor, is fixed over our repairs and cannot start until they are finished.
Solution
We erect scaffolding on the wings of each building and repair the concrete façade by façade. In each damaged area the concrete is broken out until the unsound material is removed and the reinforcement exposed, the rust is cleaned off, an epoxy-resin bonding coat is applied and the section is rebuilt with structural repair mortar. The project requires a minimum strength of 40 N/mm² and a thickness of 20 mm. A re-alkalising coating that protects the concrete is applied on top.
Each area broken out is measured on site, one by one, during the visits with the site direction. On the north-west façade of the third floor of El Carmen alone, 37 areas were recorded, adding up to 17.1 m². The same treatment has been applied inside the floors, on the columns, on the roof parapets and on the soffits of the terraces.
The work is organised so as not to interrupt activity. We began with El Carmen, whose upper floors are empty, and went on to Fernando III. There, the façade beams are demolished with a pneumatic breaker in the afternoon only. To demolish the beams of the central core of El Carmen, a mini-excavator with a breaker was lowered through the opening of the core itself with the tower crane.
On the roofs, the gravel, the insulation, the bituminous membranes and the old screed to falls are removed. The new falls are then formed, outlets and downpipes fitted, the roof waterproofed with a double bituminous membrane and finished with extruded polystyrene insulation and gravel. At Fernando III, each wing was flooded to check that no leaks appeared on the floor below, under the supervision of CEMOSA.
Result
The works began on 2 February 2026 and are still in progress. The maximum period set in the project for this lot is 16 months.
According to the site minutes of 20 October 2026, at El Carmen the concrete repair is complete on the façades of the four wings, inside the three floors, on the columns, on the roof parapets and on the soffits of the terraces. The parapets of the first-floor terraces remain. The falls of the roof are in place on all four wings and waterproofing is under way.
At Fernando III the repair of the façades is complete, except for the parapets of the four mezzanine terraces. The downpipes, the first fix of the air conditioning and the bases of the two escape stairs are also done. The roof was checked and approved after the flood tests at the visit of 27 October.
At 31 October 2026, the ninth certificate records 1,129.63 m² of concrete broken out, 1,039.13 m² repaired with structural mortar and 3,767.65 m² of roof waterproofed.
Before

The El Carmen building before the works, 2 October 2025 
Upper floor of El Carmen, cleared, before the works
During the works

Scaffolding on a wing of El Carmen, 14 April 2026 
Façade with the concrete repaired, 29 September 2026 
Demolition of reinforced concrete in the central core, 27 October 2026 
Waterproofing of the roof, 30 October 2026
Drawings and diagrams

Project drawing 23: structural repair, south-west elevation of El Carmen