Work · Camarín de Jesús

Repairing the valleys, lead flashings and gutters on the roof of a protected building

The roof of the Camarín de Jesús, in the old town of Jaén, was letting water in through valleys, flashings and gutters. We repaired those points with zinc, lead and the salvaged tiles, from scaffolding and with rope access.

Location
Jaén
Year
2023
Client
Jaén City Council
Design and site management
Servicios técnicos del Ayuntamiento de Jaén
Type of work
Rehabilitation
Slopes of curved clay tiles with a zinc sheet valley between them; behind, the roofs of the old town of Jaén and the mountains.
Roof with the zinc valley finished, 27 October 2023

Objective

The Camarín de Jesús stands on the Carrera de Jesús, in the old town of Jaén, and the municipal project records its status as an Asset of Cultural Interest. The tiled roof was in good condition overall, but the elements that carry rainwater away were failing and the leaks were causing widespread damage inside.

Jaén City Council awarded us the repair of those points: the valleys of the crossing and the nave, the lead flashings of the gable walls, the gutters and downpipes, the gutter against the adjoining building and the roof of the volume behind the altar wall.

Difficulties

  • A small job on a protected building. The project itself describes the work items as of “great simplicity”: the task was to correct construction defects, not to rebuild the roof. The demand lay in the care: salvaging the existing tiles, replacing lead with lead and forming valleys and gutters in zinc.
  • Repairs spread across the whole roof. Over some 532 m² of roofs there were five different interventions, most of them linear and at junctions: valleys, gable copings, eaves and the party wall.
  • All from outside and at height. Except for the volume behind the altar, the work was done from outside. The bill of quantities provides for tube scaffolding on three façade panels, lifelines and edge guardrails.
  • A building in use. The project required the Camarín to stay in service and the least possible disturbance in a street with pedestrian and vehicle traffic.
  • The wind. The drawing of the works asks for enough fixings on the lead sheets, so that the wind does not lift them again, and on the gutters and downpipes, so that they do not deform.

Solution

We erected tube scaffolding on the façades and worked on the roof slopes with harnesses and lifelines.

At the valleys we lifted the tiles by hand over 40 cm on each side, salvaging them to be laid again. We made good the bed, fitted a zinc sheet valley and relaid the curved clay tiles over the edge of the sheet, which is what prevents leaks. The project lays down that, if new tiles are needed, they must be identical to the existing ones.

On the gable walls we lifted the lead flashings in poor condition and replaced them with 2 mm lead sheet, with rolled joints, fixing clips and copper nails with lead washers.

We took down the gutters and downpipes and fitted 0.6 mm zinc gutters and titanium-zinc downpipes 100 mm in diameter.

At the gutter against the adjoining building, which is taller than the Camarín, we made good the bed, waterproofed it with slate-faced bituminous membrane, fitted insulation and a zinc gutter, and formed the junction with the wall in zinc sheet set into a chase.

On the volume behind the altar we removed the metal-sheet roof without touching the structure, fitted a steel subframe over the existing one and covered it with sandwich panel. Inside, a suspended ceiling of boards was fitted with insulation and ventilation grilles to prevent condensation.

For a downpipe and waterproofing on a wall with no scaffolding we subcontracted a rope-access firm, which signed up to the site’s health and safety plan and worked suspended on ropes in the second half of August.

Result

The City Council took over the works on 4 September 2023, two months after the setting-out certificate. The project estimated a period of two months. The handover certificate records that the works were carried out in accordance with the project and were in good condition, and with it the one-year guarantee began. The quantities certified match those of the project.

Before

During the works

After

Drawings and diagrams

Sheet 05 Contact

Let’s talk

Tell us about your problem or project. For enquiries in English, please write to us by email.

+34 953 291 886info@toledanoedifica.com

Contact and office hours